To be clear, Brookline’s 18 month delay applies only to NR or NR-Eligible properties. The non-NR delay is 12 months.
Also, Brookline is a CLG and because of that the town accepts that for purposes of the By-law the Commission’s determination that a property is NR Eligible is sufficient.
Dennis De Witt
Brookline
> On Jan 14, 2019, at 11:39 AM, Roughan, Michael <Michael.Roughan at hdrinc.com> wrote:
>
> Thanks to the counsel of Dennis De Witt and Gretchen Schuler, the Hopkinton Historical Commission is looking to extend our Demo Delay from 6 months to 18 months. The rationale is 18 months is sufficient time to create a single structure Historic District, if that is the course Town Meeting wished to take. We have one significant property that the applicant has submitted a demolition application for, the Davis House. This structure was built in 1794 and has a long list of events that occurred on the property.
>
> Does anyone have any information they have prepared for their Town Meeting to support a Demo Delay? What I was thinking is a list of questions i.e. Why extend the demo delay? How will it affect my property? Etc. or stories about properties lost.
>
> Also is there a list anywhere of the Ma. towns with their current demo delay length?
>
> Regards,
>
> ….Mike
>
> Michael Roughan, AIA, EDAC, LEED AP, ACHA
> Chairman - Hopkinton Historical Commission
>
> Town of Hopkinton
> 18 Main Street
> Hopkinton, MA 01748
>
> D 617.357.7725 M 617.784.6463
>
>
>
> _______________________________________________
> MassHistPres mailing list
> MassHistPres at cs.umb.edu <mailto:MassHistPres at cs.umb.edu>
> http://mailman.cs.umb.edu/listinfo/masshistpres <http://mailman.cs.umb.edu/listinfo/masshistpres>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://mailman.cs.umb.edu/pipermail/masshistpres/attachments/20190114/ac9817e1/attachment.html>
More information about the MassHistPres
mailing list