In Bolton we have a Demolition Permit application requirement that we be
allowed to photograph the structure to be demolished. This allows us
both to record the structure (interior and exterior) for posterity and
the opportunity to do a physical inspection. We usually do this onsite
work before meeting to address the application. We consult with the
Building Inspector as necessary. This has worked very well and I don't
see that anything would be gained by mandating additional BI action.
We have found that there is no substitute for Historical Commission
first hand inspection.
Regards,
Bob Busch
Co-Chair Bolton Historical Commission
On 5/20/2020 12:15 PM, Eric Dray wrote:
>
> Hamilton is looking to update their procedure for demo delay review. A
> question has arisen about whether the Commission can require/ask the
> Building Inspector to make an assessment of a building’s condition,
> especially when an assessment has been submitted by the applicant
> which may be suspect. Do any other towns have experience with this?
> Does that process need to be embedded in the bylaw?
>
> Thank you… Eric
>
> Eric E. Dray, MA JD
>
> Eric Dray Consulting
>
> 71 Prentiss Street
>
> Cambridge, MA 02140
>
> 508.566.3797
>
> www.EricDrayConsulting.com <http://www.ericdrayconsulting.com/>
>
>
> _______________________________________________
> MassHistPres mailing list
> MassHistPres at cs.umb.edu
> http://mailman.cs.umb.edu/listinfo/masshistpres
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://mailman.cs.umb.edu/pipermail/masshistpres/attachments/20200522/3fcbe1a0/attachment.html>
More information about the MassHistPres
mailing list